Todays progress; Still very slow but moving forward.
I wired up the rod locker lights, tested it and installed it and tan the leads. Swivel bases were installed on top of some .080” or .100” thick neoprene gaskets That I made. (Which I hope doesn’t react with the vinyl) I have to figure out a quick removal attachment for the sleeper seats so it looks good when the swivel seats are used.
I marked existing rivet hole locations on rib ends using a good idea from
@renns and target locations for new ones. I had to do some styro shaving as there was a few high spots but I think the boards are ready for fastening once I lay out the rivet pattern.
I mocked up a few items. Wondering about making the side board longer to hide the gap at the floor to hull. Maybe terminating the side board into the console front wall. I’m also thinking about adding a board above it under the console so I can mount fuse blocks and bus bars. Thoughts on this? Anyone else do this?
Also considering re-cladding and reusing the sliding doors at the splashwell. I don’t particularly like this set up or design, but it looks like a mess left wide open, so until I re-work the splashwell, it will have to do. The track was petty rough. I straightened it out. Some work with some files and nylon wire wheels will clean it up enough so it’s not offensive. Again, it’s probably temporary.
Tomorrow I’ll have the floor riveted and then I can wrap the last piece. I’m going to mock up the consoles and figure out the V-bench new configuration. The footwell is going to be smaller to create more storage beneath. I’m concerned with the footwell size being to tight. Anyone reconfigure this for the same reason and find it either worked well or was too cramped?