Been a while since I have been able to do any updates. Still working on the project and back in the office. Got the boat over to my welder and we fixed up the drain plug that was bugging me and closed up the splashwell
Before going to welder
Tacking pieces into place
Redrilled splashwell drain hole as it was off by 1 1/4"
Finished and grinded down on the outside to make flush
Interior view
I did have the transom U-bolts closed up as the U-bolts I got when Gander Mountain closed are bigger. Plus this will allow me to move them around for better positioning. Thinking about pushing them almost to the edge and go through the aluminum transom plates on the edge as well.
After wheel grinding and cleaning everything with acetone, I painted the lower part of the splashwell and floor to help protect the aluminum in that area because of all the pitting that was already there. I had previously filled the pitting with JB Weld.
Transom bracket installed and holes drilled for knee brace/test fitting. You will notice I did cut a hole for a new drain plug at the very bottom of the hull.
Adding 5200 liberally to parts before install
Knee bracket installed with plates
Now that this is done, I have plans for my Dad and Brother to come over this weekend to help me flip the hull. Once flipped, will be wheel grinding the 5200 to smooth it out and make it look pretty before painting with the epoxy paint. Hopefully the weather will stay warm enough, otherwise it will take forever for it to cure.